- The North Wellington PT Study considered four “Scenarios” with convert the line into a Busway being the most popular but the Labour government said keep the trains.
- The consultants report also recommended “Do Minimum” which was to keep the line.
- LGWM did not even consider reviewing this decision so now it is time to check how this recommendation was fixed.
Post Date: <span>2006</span>
- The SKM Stage 3 Report recommended keeping the Johnsonville Line because no bus Scenario had a better Benefit Cost Ratio
- But the SKM Stage 3 Report recommended “Base Case” excluded the cost of buying any replacement EMU trains and other costs as well
- Excluding these costs hid that the Bus-On-Street Scenario had the best Benefit Cost Ratio
This post follows The North Wellington Public Transport Study (2006) which is the introduction this series of posts on “How to Fix a Transport Business Case for Rail” and will focus on how the “Do Minimum” Rail Base Case Benefit Cost Ratio was fixed in the SKM Stage 3 Report to help it come first.… Read more ...
- The SKM Stage 3 Report recommended keeping the Johnsonville Line because no bus Scenario had a better Benefit Cost Ratio (BCR)
- But the SKM Stage 3 Report included tens of millions in costs in the Bus-On-Street that were not required to implement this Scenario
- Including these costs hid that the Bus-On-Street Scenario had the best BCR
This is the 3rd in this series of posts on “How to Fix a Transport Business Case for Rail” and it is recommended that the introduction post, The North Wellington Public Transport Study (2006) and then How to Fix a Transport Business Case for Rail – Part 1 Jack Up the Rail Option BCR are read first to provide context.… Read more ...
- The SKM Stage 3 Report recommended keeping the Johnsonville Line by fixing the BCRs to hide that its modelling showed the Bus-On-Street Scenario was the best performing option.
- The Bus-On-Street Scenario only performed so well because the model invalidly included billions of future transport project improvements meaning future roads would be congestion free.
Golden Mile Capacity Assessment
Date: 3 August 2006
Author: Opus International Consultants Limited (Wellington) for Transit NZ (Now NZTA)
Link to Report: https://www.scribd.com/document/390814514/Wellington-Golden-Mile-Capacity-Assessment-Summary-Final-OPUS-2006
Study Back ground and Objective
To quantify the bus capacity for the ‘Golden Mile’ route from the Wellington Railway Bus Interchange to Courtenay Place.… Read more ...