  • The North Wellington PT Study considered four “Scenarios” with convert the line into a Busway being the most popular but the Labour government said keep the trains.
  • The consultants report also recommended “Do Minimum” which was to keep the line.
  • LGWM did not even consider reviewing this decision so now it is time to check how this recommendation was fixed.
Read more ...

Public Transport

  • The SKM Stage 3 Report recommended keeping the Johnsonville Line because no bus Scenario had a better Benefit Cost Ratio
  • But the SKM Stage 3 Report recommended “Base Case” excluded the cost of buying any replacement EMU trains and other costs as well
  • Excluding these costs hid that the Bus-On-Street Scenario had the best Benefit Cost Ratio

Picture of a Train up high on Jacks

This post follows The North Wellington Public Transport Study (2006) which is the introduction this series of posts on “How to Fix a Transport Business Case for Rail” and will focus on how the “Do Minimum” Rail Base Case Benefit Cost Ratio was fixed in the SKM Stage 3 Report to help it come first.… Read more ...

Public Transport

  • The SKM Stage 3 Report recommended keeping the Johnsonville Line because no bus Scenario had a better Benefit Cost Ratio (BCR)
  • But the SKM Stage 3 Report included tens of millions in costs in the Bus-On-Street that were not required to implement this Scenario
  • Including these costs hid that the Bus-On-Street Scenario had the best BCR

Cartoon Image of a Bus being sunk into a hole

This is the 3rd in this series of posts on “How to Fix a Transport Business Case for Rail” and it is recommended that the introduction post, The North Wellington Public Transport Study (2006) and then How to Fix a Transport Business Case for Rail – Part 1 Jack Up the Rail Option BCR are read first to provide context.… Read more ...

Uncategorized

  • The SKM Stage 3 Report recommended keeping the Johnsonville Line by fixing the BCRs to hide that its modelling showed the Bus-On-Street Scenario was the best performing option.
  • The Bus-On-Street Scenario only performed so well because the model invalidly included billions of future transport project improvements meaning future roads would be congestion free.
Read more ...

Public Transport

  • In 2006, the SKM Stage 3 Report recommended a Do Minimum “Base Case” based on replacing the old English Electric EMUs with refurbished Ganz-Mavag EMUs.
  • In 2010, the GWRC then announced that new Matangi EMUs would operate on the Johnsonville Line.
Read more ...

Public Transport

How many Commuters will a future Wellington’s have and what Mode will they be using?

* Lets Get Wellington Moving expects about 17,000 more peak hour commuters will travel into the CBD by 2036
* But there’s a problem because the Wellington City Council predicts many more future residents and so this may mean over 35,000 more commuters
* The commitment to handle the majority of future commuter growth by bus and rail public transport means majors increases in the capacity of both are needed

Wellington City is facing two huge challenges, how to house more people in a city with the highest housing prices in the country and how to improve transport for all the city’s residents.… Read more ...

Active Mode Public Transport

* Understanding the funding of bus and rail services is an essential part of understanding the value of spending $301M on bus and rail services to different parts of the Wellington Region

* Greater Wellington Regional Council (GWRC) collects about $70M in Transport Rates to help make up the difference between fares and bus/rail costs – but not all ratepayers are being charged equally.… Read more ...

Public Transport